May
19, 2008
Morning Star receives permit to begin construction of runway,
north taxiway, and tie down area!
May
14, 2008
Received first comments on Final Plat from Cochise County. Review
meeting set for June 4th.
May
5, 2008
Valley Telephone Cooperative agrees to provide broadband fiber–optic throughout Morning Star Airpark.
April
17, 2008
The Final Plat and Paving, Grading, and Water Plan filed with
Cochise County.
February
18, 2008
Work begins on the Dept. of Real Estate's Public Report process.
February
13, 2008
Cochise County Planning Commission unanimously approves
Morning Star's Tentative Plat in its evening hearing.
February
4, 2008
Water plant design is completed by EEC of Tucson and
is ready for submittal to AZ Department of Environmental Quality.
February
4, 2008
Hydrology study is complete and ready to submit to AZ
Department of Water Resources for 100 year adequacy determination.
February
1, 2008
LMT Engineering completes geotechnical study and report for foundation
designs of condominium hangars and water plant storage facilities.
January
16, 2008
Cochise County Subdivision Committee approves
Morning Star's tentative plat and schedules it for February 13th
Planning Commission meeting.
December
27, 2007
Turner
Labs of Tucson completes a source water analysis for Morning Star's
new domestic well. Organic & inorganic compound tests were
easily passed, and our new water source has only 240ppm total
dissolved solids! An exceptionally low level of water hardness
for Arizona.
December
21, 2007
EEC
of Tucson issues response to Cochise County's Review Comments
of Tentative Plat.
December
4, 2007
LMT Engineering completes and issues its Geotechnical Engineering
Report for Morning Star Airpark.
November
6, 2007
Reservations hit record
rate at one per day on average in first week of November. Only
25 taxiway lots still available in Phase 1!
October
30, 2007
Geotechnical engineering
and soils study began and will be completed by mid-November.
October
26, 2007
Arizona Department of Environmental Quality approves the
domestic water master plan.
October
25, 2007
Residential water well is complete and capable of producing
4x the airpark's calculated water needs.
October
2, 2007
Domestic water master plan completed by EEC and submitted
to Arizona Department of Environmental Quality.
September
19, 2007
The Tentative Plat is filed with Cochise County for review.
September
12, 2007
Attorney Larry Robertson is contracted to form the Water Users
Association.
June
20, 2007
Chuck M. Dickens is contracted to do the Arizona Department
of Water Resources application for Water Adequacy.
June
18, 2007
Morning Star Airpark takes possession of its future home.
This beautiful 483 acre farm will remain in alfalfa production
for the remainder of 2007.
June
15, 2007
Environmental Engineering Consultants of Tucson, AZ, accepts
contract to begin the subdivision preliminary plat.
June
11, 2007
Topo, Boundary, and Design Survey completed.
June
5, 2007
Interest in Morning Star Airpark is gaining momentum through
preliminary and word of mouth advertising. The list of interested
aviators is growing daily.
April
30, 2007
Arizona Dept of Real Estate approves Notice of Intent to accept
lot reservations. The public report process is now pending.
March
29, 2007
Cochise County approves a concept drawing of the subdivision
plat.
March
14, 2007
In a unanimous decision
Cochise County Planning Commission grants
a Special Use Permit for Morning Star Airpark allowing a 60' x
4000' hard surfaced runway and related facilities.
February
22, 2007
The Federal Aviation Administration
approves Notice of Landing Area Proposal after completing an airspace
study.
Tel
(520) 826-2112
info@morningstarairpark.com
Currently accepting lot reservations!
A
public report is pending on this development.
|